Demolition of one MBTA Station Begins

Demolition work begins this week at the South Attleboro MBTA station. According to CBS 12 in Providence, the work is expected to continue through June and will include the removal of the pedestrian bridge, along with the ramps and stairs around the station area. Construction crews will complete the demolition work during the overnight hours from Sunday through Thursday and tell commuters and residents to expect noise from heavy machinery between 10 p.m. and 5 a.m., alongside light towers and generators. State Rep. Jim Hawkins estimates the construction will be completed in a few years, noting the project is not yet fully funded.